What does the full ordering and delivery timeline look like for a benching system?

The typical timeline for a commercial benching order: (1) measure and finalize layout — 1–3 days; (2) receive and review quote — 1–2 days; (3) order placement and production — 3–8 weeks depending on manufacturer and customization; (4) freight delivery — 3–7 business days from ship date; (5) installation — 1 day for small runs. Total from order to move-in: typically 4–10 weeks. If you need benching fast, ask about quick-ship or in-stock options which can arrive in 1–2 weeks. FindOfficeFurniture.com can check in-stock availability for your layout — call 888-719-4960 for the fastest path to your new benching.